The same press release ran four times this week. A chemicals plant in Mithapur, two Platinum awards at the 21st CII National Six Sigma Competition, four outlets printing one PDF. Congratulations to the teams – I know how many night shifts sit behind a storyboard, and this is peak season for the belt economy. Now the uncomfortable part. Nobody has ever entered a control plan in a competition, because a control plan has no finale. There is no category for "chart still boring in month eighteen".
What the judges actually scored
A Six Sigma competition scores a story. The rubric rewards narrative arc – a problem with teeth, a measurement phase with visible discipline, a clever analysis, a clean before-after chart, closure. That is a competition about the first four letters of DMAIC. Everything up to Improve fits on a storyboard. Control, the phase where the gain is handed to people who never sat on the project team, is where storyboards stop and plants begin.
Survivorship bias is baked into the format. You submit the project that ended well. The thirty that stalled in Analyse, or whose gains evaporated two quarters after closure, never fill in an entry form. A competition is therefore a showcase of closed projects, which is a different species from a stable process. A closed project proves a team solved a problem once. A controlled process proves the plant solves it every shift without the team. A judge sees a savings curve that ends on a high note. I see a chart that ends, full stop.
Where the money lives after the applause
At SNOP I ran quality for a greenfield plant – 900-plus people, the QA and QC function built from the ground up, which meant every control plan was written from zero because there was no "how we have always done it" to inherit. We took defect costs down 70% and held customer satisfaction at 98%. No competition entry. No trophy. What held those numbers was the least glamorous machinery in the trade: a daily quick-response meeting with real parts on the table every morning, reaction plans that actually fired, SPC charts somebody still owned after lunch, layered audits that caught drift before the customer did. The same muscle – QRQC, A3, Q-Wall – bent the failure-cost curve at WITTE Automotive and kept it bent.
Most Six Sigma gains do not die loudly. They die quietly at handover, one changeover or one shift rotation after the certificate is framed. The Black Belt rolls on to the next project. The champion is promoted out of reach. The trained operator takes her skills elsewhere, and a new fixture introduces a failure mode the control plan never met.
Projects are judged by how they end. Plants are judged by how they begin again, every shift, for years.
How to interview a Black Belt
Recruiters and plant managers treat a Platinum listing as a hiring signal, and I understand the temptation – it is pre-screened, it is public, it fits in a spreadsheet. It certifies that someone told a disciplined story under deadline. It says nothing about whether the process still behaves. Three questions do that job better than any trophy list.
- Show me the control chart from six months after closure. Not the improve-phase chart with its dramatic step change – the boring one, ideally with an annotation where an operator escalated a drift in week nine. If it does not exist, the project was a report.
- What happened to the gain at the next changeover? Ask for the week the new tooling went in and what the reaction plan did about it. A process builder knows the date. A plaque collector reaches for the savings slide.
- Would the awarded process pass a VDA 6.3 audit at 07:30 today? Auditors do not score narrative arc. They open the control plan, check whether the reaction plan fired the last three times it should have, and ask the operator on the line what she does when the chart trends. IATF 16949 asks the same question in different grammar.
If the answer comes back as the savings number again, you are being told the story. The savings number is where the question starts, not where it ends.
The award worth framing is the non-event
The same week's industry pages debate whether India's manufacturing ambition must move from making to inventing. Ambition of that scale will not be carried by award cabinets. It will be carried by control plans that survive audits, changeovers and shift rotations in ten thousand anonymous plants. The best quarter I ever signed had nothing attached to it: zero critical customer escalations, customers who did not call, a war room that stayed dark. There is no Platinum category for silence. The work that holds a plant together produces nothing to photograph.
Key takeaways
- Competitions certify the best-told DMAIC story, not the best-controlled process – survivorship bias sees to it that only projects which ended well ever reach a jury.
- The money is held or lost in control and transfer: reaction plans that fire, SPC someone still reads, layered audits and a daily QRQC cadence outlast any improve-phase chart.
- Interview belts on sustainment evidence – the post-closure control chart, the gain's fate at the next changeover, and whether the process would pass a VDA 6.3 or IATF 16949 audit today.
- The prize worth shelf space is the non-event: a quarter with zero critical customer escalations has no jury, no category and no press release – which is exactly its value.
So congratulate the winners, mean it, and then walk back out to the shop floor. The plaque goes in reception; the process goes on shift. Trophies are awarded for projects. Plants are run on process. If you want to frame something that matters, frame the quiet quarter – and then check, the following quarter, whether it repeats.